Exam4Training

What should you do?

Your organization uses Project Professional 2013 and Microsoft SharePoint 2013.You are responsible for a project with resources in different offices.All offices share the same SharePoint intranet, and all resources have valid accounts to log into the company intranet.Your project plan already has the correct names and assignments for each resource involved in this project.You need to share and receive project plan updates dynamically with your resources.

What should you do?
A . Sync with SharePoint Tasks List, automatically creating a Project Site synchronized to your Project Plan.
B . Copy and paste the project tasks to a SharePoint task list.
C . Create the Project Site in SharePoint and upload the project plan to the project site.
D . Create the Project Site in SharePoint and save the project plan to the project site.

Answer: A

Exit mobile version