What should the team member do before implementing the update?

A team member realizes that a technical update will improve a product’s performance.

What should the team member do before implementing the update?
A . Include new scope in the network breakdown structure (WBS).
B . Communicate with the project manager.
C . Document the change in the issue log.
D . Generate a change request.

Answer: D