A project team in charge of implementing Slack plans to check in with their executive team three months after the launch. The goal of this check-in meeting is to define the success of Slack at the organization.

What should the team do to prepare for this milestone most effectively?
A . Show the progress that has been made on configuring single sign-on (SSO) and training the IT help desk team on Slack’s admin capabilities.
B . Meet with key business units to identify and measure opportunities to improve productivity using Slack.
C . Prepare to show the executive team the admin console so they understand the depth of settings and policies available in Slack.
D . Display the number of weekly active members in Slack, trending from the beginning of the launch to the three-month mark.

Answer: C