What should the team do next?
A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below.
What should the team do next?
A . Continue with the sprint as the progress shows buffers for potential interruptions.
B . Ask the product owner if some low-priority stories could be cut from the sprint.
C . Continue with the sprint work as planned and keep monitoring.
D . Ask the project team to select any additional stories as they have additional capacity than planned.
Answer: B
Latest PMP Dumps Valid Version with 721 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments