A Scrum team is in a sprint retrospective at the end of a sprint. The Scrum Master facilitates this meeting and has made a simple board with headings of Keep Start and Stop Team members can post their thoughts for removing impediments.
Most ideas can be grouped together and involve the team’s own process. There are some more general suggestions to lift impediments which do not fit into the general groupings. These ideas have to do with the organization’s enterprise architecture and data compliance policy
What should the Scrum Master do with these ideas?
A . Add them to the organizations continuous improvement backlog
B. Ask the team members themselves what they want to do with them
C. Decide to add them to the team’s continuous improvement backlog
D. Ignore them because they are not relevant to this sprint or the next
Answer: B