What should the Scrum Master do?
Five new Scrum Teams have been created to build one product. A few of the developers on one of the Development Teams ask the Scrum Master how to coordinate their work with the order teams.
What should the Scrum Master do?
A . Teach the Product Owner to work with the lead developers on ordering Product Backlog in a way to avoid too much technical and development overlap during a Sprint.
B . Teach them that it is their responsibility to work with the other teams to create an integrated Increment.
C . Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint.
D . Visit the five teams each day to inspect that their Sprint Backlogs are aligned.
Answer: B
Explanation:
According to the Scrum Guide1, when multiple Scrum Teams are working together on the same
product, they must mutually define and comply with the same definition of “Done”, which includes
creating an integrated Increment at least by the end of each Sprint. The Scrum Master should teach
and coach the Developers that it is their responsibility to work with other Scrum Teams to create an
integrated Increment that meets the definition of “Done”. The other options are not aligned with
Scrum values and principles.
Reference: Scrum Guide
Latest PSM I Dumps Valid Version with 197 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund