What should the project team have done differently to avoid this error?
The LEED reviewer advised a project team that an inappropriate rating system was chosen for a newly constructed school in operation for one year and undergoing minor improvements.
What should the project team have done differently to avoid this error?
A . Allow the LEED Project Administrator sole responsibility to review the appropriate rating system for the project
B . Select LEED for Schools New Construction and Major Renovations Rating System, as this project is classified as a school
C . Select LEED for Existing Buildings: Operations and Maintenance Rating System, as the Operational and Maintenance phase has begun
D . Review the appropriate rating system and determine the best adaptation to use with consultation from U.S. Green Building Council
Answer: C
Explanation:
The project team should have selected LEED for Existing Buildings: Operations and Maintenance Rating System, as the operational and maintenance phase has begun for a newly constructed school in operation for one year and undergoing minor improvements. The LEED rating systems are designed to address the specific needs and characteristics of different types of buildings and projects. The project team should choose the most appropriate rating system for their project based on the scope, scale, and goals of the project. The LEED for Existing Buildings: Operations and Maintenance Rating System is intended for buildings that are already in use and want to improve their performance and sustainability through best practices in operation, maintenance, renovation, and occupant engagement1.
Reference: LEED v4 Green Associate Candidate Handbook1, LEED v4 O+M Reference Guide