What should the project manager use to determine this?
During a project, several risks are identified. The project manager wants to determine what risks will have the most potential impact.
What should the project manager use to determine this?
A . Sensitivity analysis
B . Expert judgment
C . Probability distributions
D . Interviewing
Answer: A