What should the project manager share with the key resource?

During an ongoing project a key resource asks the project manager about the project purpose and if it is aligned with the organization’s strategy.

What should the project manager share with the key resource?
A . The updated benefits management plan
B . The updated scope management plan
C . The updated project management plan
D . The updated communications management plan

Answer: A