What should the project manager mainly make reference to?
At the end of a project, the project manager was asked to provide a performance rating of the project team members.
What should the project manager mainly make reference to?
A . Feedback from the project sponsor
B. Agreed-upon key performance indicators (KPIs)
C. Input from project stakeholders
D. Competencies of team members
Answer: B