What should the project manager have the project team update to ensure proper communications to stakeholders?
A project manager is leading a project with several stakeholders in other functional areas of the company One of these stakeholders has just been promoted to lead another functional area, and remains a stakeholder for this project
What should the project manager have the project team update to ensure proper communications to stakeholders?
A . Project management plan
B . Stakeholder engagement plan
C . Stakeholder register
D . Communications management plan
Answer: B