Exam4Training

What should the project manager have done to avoid this?

Anew project manager was assigned to a project during implementation. The project manager realized that new tax policies are creating a risk for a cost overrun by 25%. The project manager updated the risk register and kept the project running as normal. The CEO has announced that the project could be cancelled since the acceptable cost overrun is only 20%. The project manager was quite surprised as this was new information.

What should the project manager have done to avoid this?
A . Implemented the communications management plan properly.
B. Ensured the risk tolerance of the company was properly updated.
C. Provided a proper risk response.
D. Implemented the stakeholder engagement plan correctly.

Answer: A

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version