What should the project manager have done to avoid this?

A design team discovers that the work breakdown structure (WBS) created by the project manager is missing key tasks.

What should the project manager have done to avoid this?
A . Reviewed historical information from previous projects
B . Developed an Ishikawa diagram
C . Created a requirements traceability matrix
D . Sought expert judgment from subject matter experts (SMEs)

Answer: C