What should the project manager have done to avoid this?

A manufacturing plant project is ready for hand-over to the maintenance manager. The

maintenance manager advises that the new plant is noncompliant with the company’s maintenance standards.

What should the project manager have done to avoid this?
A . Updated the communications management plan
B . Used expert judgment
C . Conducted a stakeholder analysis
D . Generated a change request

Answer: C