What should the project manager have done to avoid this?
A manufacturing plant project is ready for hand-over to the maintenance manager. The
maintenance manager advises that the new plant is noncompliant with the company’s maintenance standards.
What should the project manager have done to avoid this?
A . Updated the communications management plan
B . Used expert judgment
C . Conducted a stakeholder analysis
D . Generated a change request
Answer: C