What should the project manager have done differently?
Five agile teams working together on a product recently performed release planning Midway through the project, each team showed that their progress was on track When all of the teams integrated at the product level, many integration issues were observed. The overall product release progress declined with predictions showing the committed content will not be able to be accomplished
What should the project manager have done differently?
A . Formed a separate quality assurance team to test all items coming from each team at the end of each sprint
B . Performed a Scrum of Scrums on a regular basis to help the teams remove impediments
C . Ensured frequent and continuous integration of work to obtain early feedback and continuous learning
D . Arranged an online session on the integration concept and suggested tools to the teams
Answer: B