During the retrospective ceremony, the agile team is talking about the product owner’s expectations not being met.
What should the project manager have done at the beginning of the project?
A . Defined the expected agile team contribution in the creation of the backlog.
B . Assessed the capabilities of the agile team and planned for the required training
C . Defined the team ground rules and shared project vision.
D . Communicated project vision and sprint goals clearly to the team
Answer: D