What should the project manager have done?
The project manager has finished all the tasks of the project and immediately starts on a new project. A few months after beginning the new project, the accounting manager asks for confirmation of previous projects because the budget is still open with no further cash flows.
What should the project manager have done?
A . Conveyed task completion information to accounting
B . Closed the procurement process properly
C . Completed the transition process
D . Performed administrative closure of the project
Answer: D