What should the project manager have developed to prevent this?
While managing a project for a multinational company, a project manager continues to accept changes from the client to maintain a good relationship and secure new business. Three quarters of the way through the project, the budget is depleted.
What should the project manager have developed to prevent this?
A . Statement of work (SOW)
B . Change management plan
C . Cost management plan
D . Project scope statement
Answer: B