At the end of the last iteration, the customer rejects the deliverables since they did not meet the customer’s expectations .
What should the project manager have been done to prevent this situation?
A . Involved the customer more in the planning process for the project, and ensured agreement on the proceedings.
B . Included all relevant criteria in the agreed upon definition of done (DoD), and crafted a shared product vision.
C . Provided the customer with the backlog and the specified user stories at the beginning of the iteration.
D . Developed the DoD in close cooperation with all stakeholders to ensure their expectations were included.
Answer: D