A company is working on a project and is using a hybrid approach to streamline a customer service process. At the end of the second iteration, a business analyst joins the team to learn about the financial and scheduling aspects of project management.

What should the project manager do to support the business analyst?
A . Assign resources to coach the business analyst
B . Ask the business analyst to focus on their work allocation for the needs of the project
C . Create reports to inform the business analyst about the schedule and project cost
D . Provide the business analyst with access to the financial and scheduling information

Answer: D