What should the project manager do to reduce the risk of project failure?
An experienced project manager is leading an enthusiastic team but realizes the team lacks the experience to complete the job successfully.
What should the project manager do to reduce the risk of project failure?
A . Ask the sponsor to add experienced professionals to the team.
B. Assign a dedicated resource to check the quality of each deliverable.
C. Approve the appropriate training program for team members.
D. Provide team members with the necessary coaching and mentoring.
Answer: D