What should the project manager do to prevent this issue from occurring again?

During the construction of a facility project, the project manager notices that the project document does not nave the cost or mommy reports from the past two months. While meeting with the project team, the project manager requests greater focus on compliance with the processes established by the organization.

What should the project manager do to prevent this issue from occurring again?
A . Develop a contingency plan.
B . Conduct quality audits.
C . Review the quality metrics.
D . Review the communications management plan.

Answer: B