What should the project manager do to prevent this from being an obstacle to the project’s progress and success?

A key project decision requires the support of all stakeholders. The project manager now teams that one key stakeholder was not previously identified.

What should the project manager do to prevent this from being an obstacle to the project’s progress and success?
A . Review the stakeholder register.
B . Meet with the project sponsor.
C . Update the stakeholders engagement assessment matrix.
D . Conduct regular and timely reviews of the communications strategy.

Answer: C