All project team members refer to the project manager for various decisions. This causes delays for some tasks, as the project manager is usually preoccupied in meetings throughout the day.
What should the project manager do to prevent these delays?
A . Review the Pareto diagram to identify the source of delays.
B. Meet with the team in 2 weeks to respond to all of the open tasks.
C. Consolidate the decision-making authority to remain with the project manager.
D. Delegate the decision-making authority of some tasks to the team.
Answer: D