A company recently used desktop research for a feasibility study, which showed that the project is behind schedule. The project team also has concerns about the impact of scope changes on the project schedule.
What should the project manager do to keep the project on schedule while still meeting project objectives?
A . Collaborate with the change control board (CCB) to review the scope and submit any change requests
B . Submit a change request to the CCB and update the schedule
C . Update the scope and add more resources to the project
D . Update the scope and move on to the next project milestone
Answer: A