During the course of a project, the team develops negative group behaviors and becomes unmotivated and unproductive.
What should the project manager do to improve the project team’s performance?
A . Define and analyze performance metrics
B . Escalate poor performance to functional managers
C . Update the stakeholder engagement plan
D . Conduct a root cause analysis session
Answer: D