An agile team is making infrastructure changes to the human resources (HR) application system. Conflicting requirements are being submitted by various stakeholders.
What should the project manager do to help move the project forward?
A . Review documents provided by other teams, such as lessons learned and the risk matrix.
B . Attend the Scrum of Scrums to identify roadblocks and manage dependencies.
C . Study the technology to assist the team in decision-making if progress slows.
D . Encourage the stakeholders to collaborate by facilitating meetings and sharing knowledge.
Answer: D