What should the project manager do to help avoid this situation in the future?
An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures.
What should the project manager do to help avoid this situation in the future?
A . Switch to a Kanban approach, implementing features on a first-come, first-serve basis, fostering a sustainable pace
B . Review the velocity of the team over the last several sprnts and adjust the plan accordingly
C . Ask the project sponsor to approve overtime to compensate for the lack of performance while adjusting the plan
D . Replace junior team members with more experienced ones and negotiate the project scope to compensate for the budget gap
Answer: B