What should the project manager do to handle this situation?

While developing a new product, a key stakeholder expresses concern about insufficient information on product feature requirements. The product team disagrees and mentions that detailed requirements have been provided.

What should the project manager do to handle this situation?
A . Organize a discussion with the product team to clarify the missing information.
B . Redirect the stakeholder to discuss this request with the functional manager.
C . Record the new requirements and ask the product team to develop them.
D . Conduct new risk and scope analyses, identifying the missing information.

Answer: A