What should the project manager do to handle the conflict?

A newly hired team member just joined the project team and reports directly to the project manager. In the first week, this new member tells the project manager that there is a task priority conflict with hard, dependent tasks on the critical path.

What should the project manager do to handle the conflict?
A . Guide the team member on how to resolve the conflict.
B . Analyze the project schedule and look for alternatives.
C . Perform crashing and/or fast tracking of the schedule.
D . Meet the team member and try to plan a course of action together.

Answer: D