What should the project manager do to ensure timely delivery?

The project manager has initiated the project and the team’s roles and responsibilities have been assigned. In preparation for the development of the project management plan, the project manager reviews lessons learned from previous projects and discovers that the same team has been missing delivery dates.

What should the project manager do to ensure timely delivery?
A . Ask the team leader to assign other resources.
B . Update the issue log.
C . Include this in the risk register.
D . Escalate the issue to the functional manager.

Answer: C