The project’s customer has stated the project must be completed by a date indicated as the P90 date established on the Monte Carlo analysis.
What should the project manager do to ensure the P90 date is met?
A . Update the assumptions/exclusions register
B. Hire more resources and crash the schedule
C. Perform a qualitative risk analysis for the project
D. Mitigate risks identified on the sensitivity analysis
Answer: D
Explanation:
The project manager should mitigate risks identified on the sensitivity analysis to ensure the P90 date is met. Sensitivity analysis helps identify the most critical risks that have the potential to impact the project’s completion date. By mitigating these risks, the project manager can increase the likelihood of meeting the P90 date.