What should the project manager do to ensure that all the procedures are followed in the future?

A project manager joins a startup and discovers that the chief technology officer (CTO) encourages the team to overlook some procedures in the interest of speed .

What should the project manager do to ensure that all the procedures are followed in the future?
A . Develop new procedures that are easy for the team to follow.
B . Escalate the issue to the CEO and the board members.
C . Instruct the team that the procedures should always be followed.
D . Initiate a review of the procedures with the CTO and the team.

Answer: C

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments