What should the project manager do to ensure that all the procedures are followed in the future?

A project manager joins a startup and discovers that the chief technology officer (CTO) encourages the team to overlook some procedures in the interest of speed.

What should the project manager do to ensure that all the procedures are followed in the future?
A . Develop new procedures that are easy for the team to follow.
B . Escalate the issue to the CEO and the board members.
C . Instruct the team that the procedures should always be followed.
D . Initiate a review of the procedures with the CTO and the team.

Answer: C