What should the project manager do to ensure success of the project?
Due to organizational changes: several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised.
What should the project manager do to ensure success of the project?
A . Review and prioritize new requirements with stakeholders to determine which change requests are needed.
B . Escalate the issue to the project sponsor and seek support to keep the original requirements.
C . Seek immediate approval to amend the project timeline and budget in order to deliver all new requirements
D . Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project
Answer: B