What should the project manager do to ensure a successful project?
In an ongoing project, stakeholders have been approaching team members for status reports and changes without consulting the project manager .
What should the project manager do to ensure a successful project?
A . Send the project charter to all stakeholders for information.
B . Send an email to all stakeholders directing them to approach the project manager directly.
C . Review the stakeholder engagement plan and inform the stakeholders.
D . Review the change management plan and ask the change control board (CCB) to be
involved.
Answer: C