What should the project manager do to continue the project?
The portfolio management office wants to cut costs by suspending some ongoing projects that do not directly support the organizational strategy. The project manager has invested too many resources into one of the projects to be suspended, but the portfolio management office has not backed down on their plan.
What should the project manager do to continue the project?
A . Meet with the project team and revise the project goals.
B . Update the project charter to make it align with organizational strategy.
C . Demonstrate the project alignment to the organizational strategy.
D . Escalate the issue with the project sponsor to request support.
Answer: B