Work on a project passes the customer acceptance test and the customer expresses appreciation.

What should the project manager do to close the project?
A . Notify the steering committee.
B . Obtain a letter of recommendation from the customer
C . Obtain formal acceptance from the customer
D . Notify the project sponsor that work is completed.

Answer: C