What should the project manager do to avoid future delays?

During project execution, the project manager discovered that a key deliverable was missing from the scope of work After investigation, the project manager and the team discovered that the missing deliverable will impact the critical path

What should the project manager do to avoid future delays?
A . Submit a change request.
B . Add additional resources to the project
C . Update the scope of work.
D . Review the risk management plan

Answer: A

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments