A project manager is developing a schedule for a communications project. The available project information is vague.
What should the project manager do to address this?
A . Assign a contingency reserve for uncertain activities.
B . Increase the total float of all activities.
C . Determine activity durations using three-point estimating
D . Meet with the project team to estimate activity durations.
Answer: C