What should the project manager do to address this?
As part of a project, a new plant is being constructed in a typhoon-prone area. This may impact the project s schedule and quality.
What should the project manager do to address this?
A . Conduct the Perform Quantitative Risk Analysis process, and plan a risk response.
B . Establish a contingency reserve.
C . Outsource the project to transfer the risk.
D . Implement the Plan Risk Management process and establish a management reserve.
Answer: A