A project manager analyzes the cumulative flow chart and identifies a bottleneck in the testing activities from a self-organizing team. After discussing it with the team, a gap related to testing skills is identified.

What should the project manager do to address the issue?
A . Onboard a new project team member who has testing skills.
B. Provide training to the entire team so they all will be able to perform tests.
C. Support the team to identify an approach to resolve the problem.
D. Ask the development team to slow down so the testers can catch up.

Answer: C