What should the project manager do to address the issue?

A project manager analyzes the cumulative flow chart and identifies a bottleneck in the testing activities from a self-organizing team. After discussing it with the team, a gap related to testing skills is identified.

What should the project manager do to address the issue?
A . Onboard a new project team member who has testing skills.
B. Provide training to the entire team so they all will be able to perform tests.
C. Support the team to identify an approach to resolve the problem.
D. Ask the development team to slow down so the testers can catch up.

Answer: C

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments