What should the project manager do next?

for a project has reported the potential for a delivery delay due to a technical issue with the sub-supplier. To stay on schedule, the vendor proposed replacing the sub- supplier’s component with a similar part that is different from the one that is stipulated in the project specifications.

What should the project manager do next?
A . Accept the proposed replacement in order to keep procurement activities on track
B . Insist on using the component per the project specifications and air freight the equipment to mitigate the delay
C . Instruct the vendor to use the part that is compliant with the project specifications and update the schedule
D . Consult with a subject matter expert (SME) to see if the proposed change is acceptable

Answer: D