What should the project manager do next?

After preparing the work breakdown structure (WBS), the project manager is ready to assign task areas to project team members. Subsequently, the project sponsor asks to add requirements that the team feels are unachievable.

What should the project manager do next?
A . Evaluate the impact of the request on the project scope, schedule, and budget.
B . Use expert judgment to adjust the WBS based on the new requirements.
C . Review the project scope and resources to assess the feasibility of satisfying the request.
D . Collect requirements, and conduct a team brainstorming session.

Answer: A