What should the project manager do next?

A project team is planning the next sprint review. The project lead receives an email from a senior manager asking for a project status using a template that is more detailed than the one used for monthly reports sent to the project management office (PMO). The team uses an electronic product backlog and a kanban board to track the progress.

What should the project manager do next?
A . Modify the PMO template to include the information.
B. Contact the senior manager and discuss their needs.
C. Give the senior manager access to the product backlog.
D. Organize a review of the kanban board with the manager.

Answer: B