What should the project manager do next?

A team realizes that there is no access to data that the project depends on to complete the current iteration. This dependency was known; however, the team is unsure of the available options to remove this obstacle.

What should the project manager do next?
A . Guide the team to determine alternatives.
B. Move the dependent task to the next iteration.
C. Escalate the issue to the company’s IT manager.
D. Escalate the issue to the project sponsor.

Answer: A

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments