What should the project manager do next?
A customer’s technical lead discussed a new feature with the project manager. The project manager believes the new feature will boost performance significantly and adds it as a high-priority item in the sprint backlog. At the end of the sprint, all of the planned stories were not completed because the new feature took more time.
What should the project manager do next?
A . Receive an agreement from the product owner and add the new story to the product backlog.
B. Agree with the project team to modify and delete some of the stories in the current sprint backlog.
C. Obtain approval from the project team and add the new story to the product backlog.
D. Negotiate with the scrum master before adding the new story to the sprint backlog.
Answer: A