What should the project manager do next?
While reviewing signed project documentation, the project manager notices that only successes were included. The project manager discovers that learn members were reluctant to sign documents that indicated errors.
What should the project manager do next?
A . Conduct post-implementation meetings lo complete project documentation
B . Implement a recognition and rewards system to promote future reporting of errors.
C . Perform an audit to discover errors presented during implementation.
D . Start future projects with workshops focusing on the value of documentation.
Answer: D