A project is on its fifth iteration out of six. One member of the team has left the company unexpectedly.
What should the project manager do next?
A . Detail the reason for the project delay in the status report.
B. Invite the stakeholders to discuss a mitigation plan.
C. Take on some of the necessary work to minimize the impact.
D. Register an issue and escalate it to the project sponsor.
Answer: B